question

Justice avatar image
0 Likes"
Justice asked Felix Möhlmann answered

Displaying only operating hours utilization in dashboard

In my model, I am trying to display bed utilization. However, The utilization chart on the dashboard displays 100% utilization for off-scheduled time of the bed area. I want only the operating hours utilization to display. How do I take out the utilization for the off-scheduled time from the utilization chart. Below is a picture of what am talking about.

1744996191566.png

I will be gratefull with any form of help. Thank you.

FlexSim 25.1.0
dashboardsutilization
1744996191566.png (41.0 KiB)
5 |100000

Up to 12 attachments (including images) can be used with a maximum of 23.8 MiB each and 47.7 MiB total.

1 Answer

Felix Möhlmann avatar image
0 Likes"
Felix Möhlmann answered

This likely means that the bed(s) are still occupied and thus not "Off Schedule". If a location is in a non-included state for the entire duration of a chart interval no value will be shows for that interval.

You can see this in the attached example model. At the start of the off-schedule time, one bed is still occupied. The chart thus reports 100% utilization for the 10:00 time period. For the next two hours, no value is shown.

utilization-example.fsm

capture1.png


capture1.png (46.6 KiB)
5 |100000